Water Reservoir: jebel Ali, CW/380A/2003
Sub Contractor: |
Al Hijaz Mechanical Equipment CO. L.L.C. |
Client: |
Dubai Electricity &..Water Authority (DEWA) |
Consultant: |
MJS Consultant |
Reservoir Volume: |
60 Million Gallons
|
Project Period: |
6months |
Main Contractor: |
United Engineering Const. (UNEC) L.L.C. |
Scope: |
Pipework. Electromechanical Work (E&..M) &.. Instrumentation |

)ebel Ali Water Reservoir
The project consisted of the construction of a single 60 million gallon reinforced concrete water reservoir with interconnection of the pipes to the existing pipelines, including the PLC/SCADA control, telecommunication system interfacing with the existing MCC in addition to the CCTV surveillance system water quality analysers.